Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013 (RFCTLARR Act); Land Acquisition Act 1894 for older awards; Articles 226 and 300A

Government Took Your Land in Delhi? Compensation, Lapse and Rehabilitation Disputes

Land acquired in Delhi? How to raise compensation by reference and appeal, when acquisition lapses after Indore Development, and claiming rehabilitation.

In short. If the government has acquired, or wants to acquire, your land in Delhi, you can object before the award, ask for higher compensation after it through a reference and an appeal to the Delhi High Court, claim rehabilitation benefits, and in limited cases argue that the acquisition has lapsed. Deadlines are short: a reference must usually be sought within six weeks of the award. References take two to five years and appeals longer. This week, get the award, the notifications and your title papers together and have them read.

सारांश (हिंदी में)अगर सरकार ने दिल्ली में आपकी जमीन अधिग्रहित कर ली है या करने वाली है, तो आप अवॉर्ड से पहले आपत्ति दे सकते हैं, अवॉर्ड के बाद रेफरेंस और फिर दिल्ली हाई कोर्ट में अपील के जरिए ज्यादा मुआवजा मांग सकते हैं, पुनर्वास के लाभ मांग सकते हैं, और कुछ सीमित मामलों में यह कह सकते हैं कि अधिग्रहण लैप्स हो गया है। समय सीमा छोटी है: रेफरेंस आम तौर पर अवॉर्ड के छह हफ्ते के अंदर मांगना होता है। रेफरेंस में दो से पांच साल और अपील में इससे ज्यादा समय लग सकता है। इसी हफ्ते अवॉर्ड की कॉपी, सभी नोटिफिकेशन और अपनी जमीन के कागज इकट्ठा करके किसी वकील को दिखाएं।

Is this your situation?

  • A notification has been published for acquiring your land, house or shop in Delhi and you want to object.
  • The Land Acquisition Collector has made an award and the rate per bigha or per square metre is far below what land around you sells for.
  • Your land was acquired decades ago under the 1894 Act and you believe the acquisition lapsed when the 2013 Act came in.
  • Compensation was announced but never paid to you, or was paid to the wrong co-sharer.
  • Your family lost its livelihood from the land and no rehabilitation or alternative plot was offered.
  • Your land was taken for a highway, metro or railway project and you were told the 2013 Act does not apply.
  • A reference court has decided your enhancement claim and you, or the government, want to appeal.

Which law applies to your land

The first question in any Delhi land acquisition case is which statute governs it, because the rates, the time limits and the remedies all change with the answer. The Land Acquisition Act 1894 governed almost every acquisition in Delhi for sixty years, including the large notifications for the planned development of Delhi from 1959 onwards. It was replaced on 1 January 2014 by the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013, which most people shorten to the RFCTLARR Act or simply the 2013 Act.

Section 24 of the 2013 Act sorts out the old cases. If no award had been made under the 1894 Act by 1 January 2014, compensation is now worked out under the 2013 Act, even though the notification was issued under the old law. If an award had been made, the proceedings continue under the 1894 Act, with one important exception: an acquisition can be treated as lapsed under Section 24(2) in narrow circumstances explained further down.

A third category catches many people by surprise. Section 105 and the Fourth Schedule list central laws that have their own acquisition procedure, such as the National Highways Act 1956, the Railways Act 1989 and the Metro Railways (Construction of Works) Act 1978. Since 2015 the compensation and rehabilitation provisions of the 2013 Act have been applied to acquisitions under these laws too, but the procedure, the deciding officer and the route of challenge are those of the special law.

Land acquisition disputes that reach the Delhi High Court

  • Low compensation. The most common dispute by far. The award rate does not reflect sale prices of comparable land, ignores the potential of the land, or wrongly classifies it as agricultural when it was already built up or fit for building.
  • Lapse claims. Owners of land acquired under the 1894 Act who say possession was never taken and compensation never paid, so the acquisition has lapsed under Section 24(2) of the 2013 Act.
  • Compensation never paid or paid to the wrong person. Disputes among co-sharers, heirs and purchasers over who gets the money, and claims for interest where payment was delayed.
  • Rehabilitation and resettlement. Families who depended on the land, including tenants and labourers, who were left out of the rehabilitation entitlements in the Second Schedule.
  • Alternative plots. Claims under the Delhi scheme for allotting alternative residential plots to owners whose land was acquired for planned development, where recommendation or allotment has been refused or delayed.
  • Defects in procedure. Challenges to a notification issued without a social impact assessment, without hearing objections, or under the urgency clause without real urgency.
  • Appeals from reference courts. Appeals by owners seeking more and by the government or the requiring body seeking to reduce an enhanced award.

How compensation is worked out under the 2013 Act

Under Section 26 the Collector fixes the market value of the land as the highest of three figures: the minimum value under the Indian Stamp Act for registering a sale deed in that area (in Delhi, the circle rate), the average of the higher half of sale deeds for similar land in the vicinity over the previous three years, and any amount consented to in a private or public private partnership project. That market value is then multiplied by a factor which, for urban areas, is 1. Since most land in Delhi is now treated as urban or urbanisable, the multiplier rarely helps a Delhi owner the way it helps a rural owner in other states.

To that figure the Collector adds the value of buildings, trees and other things attached to the land under Section 29, valued by competent engineers or experts without deducting depreciation. Section 30 then adds a solatium of 100 per cent of the total, which is a payment for the compulsory nature of the taking, and an additional amount of 12 per cent a year on the market value from the date of the social impact assessment notification to the date of the award or of taking possession, whichever is earlier.

Most disputes turn on the sale deeds. The Collector usually picks the lowest exemplars or rejects better ones as not comparable. A good reference petition attacks this with certified copies of registered sale deeds of similar plots nearby, evidence of the location, road frontage and development around the land, and proof of what the land could actually be used for on the notification date. The circle rate is a floor, not a ceiling, and the courts have repeatedly accepted higher genuine sale prices where they are proved properly.

Older awards under the 1894 Act: what you are still entitled to

Where the award was made under the 1894 Act, the compensation is the market value on the date of the Section 4 notification, plus a solatium of 30 per cent under Section 23(2), plus an additional amount of 12 per cent a year under Section 23(1A) from the notification to the award or possession. Interest on excess compensation runs under Sections 28 and 34 at 9 per cent for the first year and 15 per cent after that. These figures are lower than under the 2013 Act, which is why so many owners tried to argue that their old acquisitions had lapsed.

A remedy that people forget is Section 28A of the 1894 Act. If a reference court enhanced compensation for some owners of land covered by the same notification, an owner who did not seek a reference can apply to the Collector within three months of that court award for redetermination at the same rate. The application is to the Collector, not to the court, and the three months run from the date of the reference court's award, so a family that hears about a neighbour's success late can lose this remedy entirely.

There is also a trap in Section 31. An owner who accepts compensation without recording protest cannot later ask for a reference under Section 18. If you are collecting the award amount, the receipt or the application should state clearly that it is accepted under protest. The same caution applies in practice under the 2013 Act.

The provisions that decide most cases

Section 15, RFCTLARR Act

Objections within 60 days of the preliminary notification, heard by the Collector, who reports to the government. This is the stage to challenge the public purpose, the extent of land and the social impact findings.

Sections 19, 21, 23 and 25, RFCTLARR Act

Declaration of the land to be acquired, public notice inviting claims, the Collector's award, and the rule that if no award is made within 12 months of the Section 19 declaration the whole proceeding lapses, unless the government extended the period for reasons recorded.

Section 24, RFCTLARR Act

The transition clause for acquisitions started under the 1894 Act, including lapse under Section 24(2) where an award was made five years or more before 1 January 2014 and neither possession was taken nor compensation paid.

Sections 64 and 74, RFCTLARR Act

Section 64 lets an aggrieved person ask the Collector to refer objections on the amount, measurement or apportionment to the Authority set up under Section 51. Section 74 gives an appeal to the High Court against the Authority's award within 60 days, extendable by a further 60 days for sufficient cause.

Sections 18, 28A and 54, Land Acquisition Act 1894

Reference to the civil court on the amount (old cases), redetermination for non-applicants after a court award, and appeal to the High Court from the reference court's award.

Has your acquisition lapsed? Section 24(2) after Indore Development Authority

Section 24(2) says that where an award under the 1894 Act was made five years or more before 1 January 2014 but physical possession of the land has not been taken or compensation has not been paid, the proceedings are deemed to have lapsed. For some years courts, the Delhi High Court among them, read 'or' to mean that either failure was enough, and many Delhi acquisitions were declared lapsed.

That changed with the Constitution Bench decision in Indore Development Authority v. Manoharlal (2020). The Supreme Court held that lapse happens only if both conditions are met: possession was not taken and compensation was not paid. If either was done, there is no lapse. The court also held that compensation is 'paid' when it is tendered to the owner, and that depositing it in the treasury is enough even if it was not deposited in court; that possession is ordinarily taken by drawing up a possession report or panchnama, and continued presence of the owner on the land afterwards does not undo it; that periods covered by court stays are excluded from the five years; and that Section 24(2) does not revive stale claims or reopen proceedings that had already concluded.

In practice, this means most lapse claims in Delhi now fail. The government's records usually show a possession panchnama or a deposit of the award amount. A lapse claim is still worth examining where the records genuinely show neither, where possession was symbolic over land that was never surveyed, or where the award covered only part of a holding. Before filing anything, Advocate B.K. Singh asks the family to obtain the possession report, the payment or deposit record and the order sheet of any earlier litigation through an RTI application or inspection, because these three documents decide the claim more than any argument does.

The proviso to Section 24(2) remains useful in a narrower set of cases. Where an award was made but compensation for the majority of land holdings had not been deposited in the beneficiaries' accounts, all beneficiaries under that notification are entitled to compensation under the 2013 Act. This is a claim for higher compensation, not for return of the land.

Rehabilitation, resettlement and alternative plots

The 2013 Act treats rehabilitation and resettlement as a separate entitlement from compensation. Section 31 requires the Collector to pass an award on rehabilitation and resettlement for every affected family, and the Second Schedule lists what they get, which includes a house in some cases, a one-time payment or annuity, a subsistence allowance and transportation costs. The definition of 'affected family' in Section 3(c) is wider than owners: it covers agricultural labourers, tenants, sharecroppers and families whose primary livelihood depended on the land for three years before the acquisition.

In Delhi, a long-running scheme of the Delhi administration provides for allotment of alternative residential plots to owners whose land was acquired for the planned development of Delhi. Applications are processed through the Land and Building Department of the Delhi government, which recommends eligible applicants, and the plot is allotted by the Delhi Development Authority. Eligibility conditions about the date of ownership, the extent of land and not owning another house in Delhi are applied strictly, and the scheme has been interpreted by the courts as a policy concession rather than a legal right. Delay in applying, gaps in the chain of title and disputes among legal heirs are the usual reasons for refusal.

Refusal of rehabilitation benefits or of an alternative plot is not a matter for a reference. It is an administrative decision, and the challenge is by representation to the department and then by writ petition in the Delhi High Court on the ground that the decision is arbitrary, applied the wrong criteria or ignored the applicant's documents. Disputes about the plot itself after allotment, such as possession, area or charges, are covered on our page on DDA flat, plot and allotment disputes.

Which court hears your case, and why

Disputes about the amount of compensation start below the High Court. Under the 1894 Act, the reference under Section 18 goes to the civil court, and in Delhi Additional District Judges in the district court complexes act as reference courts for the land in their districts. Under the 2013 Act, the reference under Section 64 goes to the Land Acquisition, Rehabilitation and Resettlement Authority constituted under Section 51. The landowner does not file the reference directly: the application is made to the Collector, who must send it on with his statement, and if he sits on it a writ of mandamus can be sought.

The Delhi High Court then hears appeals: under Section 54 of the 1894 Act against a reference court's award, and under Section 74 of the 2013 Act against the Authority's award. These are first appeals in which the High Court can re-examine the evidence on market value. The High Court also hears writ petitions under Article 226 about land in Delhi, such as challenges to notifications, lapse claims, refusal of rehabilitation and alternative plots, and non-payment of an award that has become final. Our page on writ petitions against the Central or Delhi government explains how such petitions are drafted and listed.

Land outside Delhi is a different matter. If your land is in Gurugram, Faridabad, Noida or Ghaziabad, acquisition disputes generally go to the reference court of that district and then to the Punjab and Haryana High Court or the Allahabad High Court, even if you live in Delhi. Under Article 226(2) the Delhi High Court can hear a writ where part of the cause of action arose in Delhi, for example where a central ministry in Delhi took the decision under challenge, but for land the courts usually prefer the High Court of the state where it lies. The guide on filing a writ in the Delhi High Court if you live outside Delhi covers the forum question in more detail.

For highway acquisitions under the National Highways Act 1956, the amount is fixed by the competent authority and disputes go to an arbitrator appointed by the Central Government under Section 3G(5), usually a senior revenue officer, and the arbitrator's award is challenged under Section 34 of the Arbitration and Conciliation Act 1996. The Supreme Court in Union of India v. Tarsem Singh (2019) held that solatium and interest must be paid in highway acquisitions as well.

Step by step: from notification to High Court appeal

This is the usual sequence for an acquisition under the 2013 Act. Older 1894 Act cases follow the same broad shape with different section numbers.

  1. Read the notifications and file objections

    Get copies of the preliminary notification under Section 11, the social impact assessment report and the land schedule. File written objections under Section 15 within 60 days, with your title documents and any reason why the land should be excluded or the public purpose is doubtful. Objections not raised here are harder to raise later.

  2. Lodge your claim after the declaration

    When the Collector issues the public notice under Section 21, file your claim stating your interest, the area, the structures and trees, and the compensation you seek with supporting sale deeds. A detailed claim at this stage becomes part of the record the reference court will see.

  3. Collect the award, under protest if needed

    Obtain a certified copy of the award and the Collector's notice. If you take the money, record in writing that it is received under protest, so your right to seek enhancement is preserved.

  4. Apply for a reference within the time limit

    Apply to the Collector under Section 64 (or Section 18 under the 1894 Act) within six weeks of the award if you were present when it was made, otherwise within six weeks of receiving notice or six months of the award, whichever is earlier. State each objection clearly: amount, measurement, the person entitled, or apportionment.

  5. Prove the market value before the Authority or reference court

    This is a trial. You lead evidence through witnesses and certified sale deeds, and the government and the requiring body cross-examine. Most of the eventual outcome is decided here, so do not treat it as a formality.

  6. Appeal to the Delhi High Court

    File the appeal under Section 74 (or Section 54) with a certified copy of the award and the decree, within 60 days. The government may file its own appeal, and both are usually heard together.

  7. Recover the amount with interest

    Once enhancement is final or not stayed, apply for release of the amount with statutory interest. If it is not paid, execution proceedings or a writ follow.

Where the dispute is about a decision rather than the amount, such as refusal of rehabilitation, an alternative plot or a lapse claim, the route is a representation followed by a writ petition directly in the Delhi High Court.

How long each stage takes and what it costs

StageTypical timeCourt fee and expenses (general)
Objections under Section 15Within 60 days of the preliminary notificationNo court fee; cost of certified copies and survey reports
Application for referenceWithin six weeks of the award (longer limits in some cases)No court fee on the application to the Collector in most cases; check the current rules
Reference before the Authority or reference courtCommonly 2 to 5 years, depending on evidence and adjournmentsCourt fee on the enhanced amount claimed may be payable; check the current court fee schedule
First appeal in the Delhi High CourtAdmission within weeks; final hearing often several years laterAd valorem court fee on the additional amount claimed in appeal; check the current rate
Writ petition (lapse, rehabilitation, alternative plot)First hearing within weeks; decision in months to a few yearsFixed court fee for writs plus process fee
Supreme Court special leave petitionDepends on admission; may take yearsSeparate court fee and Advocate-on-Record costs

Documents to gather before your first meeting

Acquisition papers

  • Copies of the notifications under Sections 11 and 19 (or Sections 4 and 6 under the 1894 Act)
  • Social impact assessment report, if any
  • The Collector's award and the notice of award
  • Possession report or panchnama, if available
  • Proof of payment, deposit or tender of compensation

Ownership and land records

  • Khatauni, khasra girdawari and jamabandi for the relevant years
  • Registered sale deed, gift deed, partition deed or will
  • Mutation entries and death certificates for earlier owners
  • Succession certificate or family settlement among heirs
  • Site plan, photographs and any building sanction

Evidence of value

  • Certified copies of registered sale deeds of similar land nearby, close to the notification date
  • Circle rate notifications for the year
  • Evidence of roads, colonies, markets and services around the land
  • Valuation report, if one was commissioned

Litigation history

  • Earlier writ petitions, references or appeals and their orders
  • Any stay orders and their dates
  • RTI replies from the Land Acquisition Collector or Land and Building Department

Where landowners usually go wrong

The most expensive mistake is missing the reference deadline. Families often learn of the award late, wait to see what neighbours do, or assume that a representation to the minister keeps their rights alive. It does not. The time for a reference runs from the award or the notice, and the Collector has only limited power to accept a late application. Once that window closes, the award rate usually binds you, subject to Section 28A in old cases.

The second mistake is weak evidence of value. Reference courts are courts of evidence. A bundle of newspaper advertisements, a broker's letter or unregistered agreements carries little weight. Certified copies of registered sale deeds, witnesses who can speak to them, and proof that the exemplar land is comparable in size, location and use are what move the figure. A small plot sold at a high rate may be discounted for a large holding, and the court will apply a deduction for development costs where the land is raw.

The third is family disorder. Where the recorded owner has died and the heirs have not mutated the land or agreed among themselves, the Collector may send the money to the reference court for apportionment, and years can go in that dispute alone. Sorting out succession papers early, and if possible a written family arrangement, saves time later.

Owners, heirs, buyers, tenants and NRIs: how the position differs

A recorded owner on the date of the notification has the full set of rights: objection, claim, reference, appeal and rehabilitation. Heirs step into the same position but must prove succession, and where an owner dies during a reference or appeal, the legal representatives must be brought on record within the time allowed, or the proceeding can abate.

A person who bought the land after the preliminary notification is in a weaker position. The Supreme Court held in Meera Sahni v. Lieutenant Governor of Delhi (2008), a Delhi case, that a subsequent purchaser cannot challenge the acquisition itself, because the sale after the notification is void against the government. Such a buyer may still claim the compensation that the seller would have received, but cannot ask for the land to be released or argue lapse on his own account. Buyers of plots in unauthorised colonies laid out on notified land in Delhi face this problem often.

Tenants, cultivators and labourers who are not owners cannot claim the market value of the land, but they may be 'affected families' entitled to rehabilitation benefits under the 2013 Act, and a tenant may have a claim to a share of compensation for his interest under the apportionment provisions. These claims need proof of dependence on the land for the required period: electricity bills, ration cards, crop records or rent receipts.

NRI owners are frequently the last to learn of an acquisition because notices go to the village address. A registered power of attorney in favour of a trusted relative, a current email and Indian address on the revenue record, and a periodic check of notifications can prevent a missed deadline. Our page for NRI and overseas clients explains how affidavits and vakalatnamas are signed abroad.

A made-up example: a family in a south-west Delhi village

Here's a made-up example. The Sehrawat family owns about four bighas in a village near Najafgarh. In 2016 the Delhi government issues a preliminary notification under the 2013 Act for a road and drainage project. The family files objections, which are rejected, and the Collector's award in 2018 fixes compensation at the circle rate for agricultural land, with solatium and the 12 per cent additional amount.

Two plots on the same road had been sold in 2015 by registered deeds at almost double the circle rate, because a colony had grown up next to the land. The family's lawyer advises them to collect the award amount under protest and apply for a reference within six weeks, with certified copies of those sale deeds and photographs showing the colony and the metalled road.

Before the Authority, the government argues that the exemplar plots were small and fully developed. The Authority accepts the sale deeds but applies a deduction for size and development, and fixes a rate about forty per cent above the award. The government appeals to the Delhi High Court under Section 74, and the family cross-appeals for the full rate. Both are heard together years later. Any real outcome depends on the evidence actually led.

Procedure matters too: the Article 300A line of cases

The right to property is no longer a fundamental right, but Article 300A says no person shall be deprived of property save by authority of law. The Supreme Court in Kolkata Municipal Corporation v. Bimal Kumar Shah (2024) read seven procedural rights into it, including notice, a hearing on objections, a reasoned decision, a genuine public purpose, fair compensation and a timely conclusion. An acquisition that skips these steps can be set aside.

In Vidya Devi v. State of Himachal Pradesh (2020) the Supreme Court ordered compensation to an owner whose land had been taken for a road decades earlier without any acquisition at all. Where a department in Delhi has simply occupied land for a road or drain, a writ can seek acquisition with compensation or restoration.

Writ courts do not, however, fix market value. If the complaint is that the rate is too low, the High Court will normally send the owner to the reference, treating it as an adequate alternative remedy. The guide on why writs are dismissed for an alternative remedy explains this rule, which catches many petitions.

When going to court may not be worth it

If the award rate is already close to the best comparable sale deeds, a reference may not repay the years it takes, and the government may appeal any increase. When Advocate B.K. Singh reviews a land acquisition file, he looks first at three dates: the notification, the award and the possession report. Those dates tell him which Act applies, whether any deadline is still open and whether lapse is even arguable. Only then does he look at the sale deeds to judge whether a reference is likely to move the figure enough to justify the time. Sometimes the honest advice is to take the compensation, file a Section 28A application if a neighbour's reference succeeds, and spend the energy on a rehabilitation or alternative plot claim instead.

What to do this week

Find the award date and count the six weeks. If the deadline is close, the reference application can be filed first and supported with evidence later. Write to the Land Acquisition Collector for certified copies of the award, the possession report and the payment record, and file an RTI application if copies are refused. Put your title and succession papers in order, and collect certified copies of sale deeds of nearby land close to the notification date.

If a reference court or Authority has already decided your case, note the 60-day appeal period and order a certified copy at once. If the Delhi High Court has dismissed your appeal or writ, the options are a review of the High Court judgment for an error apparent on the record, or a petition before the Supreme Court of India, each with its own short time limit. Court fees in appeals are ad valorem, and the guide on court fees in the Delhi High Court gives the general position.

To have your award, notifications and land records read, or for updates on the law on land acquisition in Delhi, contact Advocate B.K. Singh.

Frequently asked questions

How much compensation will I get if the government acquires my land in Delhi?

Under the 2013 Act you get the market value (the highest of the circle rate, the average of the higher half of comparable sale deeds and any consented amount), plus the value of structures and trees, plus 100 per cent solatium and 12 per cent a year additional amount. The actual figure depends on the sale deeds the Collector accepts. If you think it is too low, you can seek a reference.

What is the time limit to challenge a land acquisition award?

An application for reference must generally be made within six weeks of the award if you were present when it was made, and otherwise within six weeks of the notice or six months of the award, whichever is earlier. An appeal to the High Court from the reference award must be filed within 60 days. Missing these limits usually ends the right to enhancement.

Can I get my land back if the acquisition has lapsed?

Only if the award was made at least five years before 1 January 2014 and the government neither took possession nor paid or tendered compensation. After the Indore Development Authority judgment in 2020, both failures must be shown. Most Delhi cases fail on this test because the records show a panchnama or a treasury deposit.

Does the 2013 Act apply to land taken for highways or the metro in Delhi?

The procedure under laws like the National Highways Act and the Metro Railways (Construction of Works) Act continues, but the compensation and rehabilitation provisions of the 2013 Act have been applied to them since 2015. For highways, disputes on the amount go to an arbitrator and then to court under the Arbitration Act.

I accepted the compensation cheque. Can I still ask for more?

Yes, if you accepted it under protest. Under the 1894 Act, a person who accepts compensation without protest loses the right to seek a reference, and the same caution is followed under the 2013 Act. If you did not record protest, take advice quickly on whether any other route, such as Section 28A, is open.

Who gets the compensation if the land owner has died?

The legal heirs, once they prove succession through mutation, a will, a succession certificate or a family settlement. If heirs disagree, the Collector may send the money to the Authority or reference court for apportionment, which can take years. Settling succession papers early avoids this.

Can a tenant or farm labourer claim anything when land is acquired?

They cannot claim the market value of the land, but they may qualify as an affected family for rehabilitation and resettlement benefits under the Second Schedule if they depended on the land for their livelihood for three years before the acquisition. A tenant may also claim a share of compensation for his interest through apportionment.

My land is in Gurugram but I live in Delhi. Which High Court do I go to?

Usually the Punjab and Haryana High Court, because the land and the acquisition are in Haryana. The reference also goes to the court or authority in that district. The Delhi High Court may hear a writ only where part of the cause of action arose in Delhi, and courts tend to prefer the High Court where the land lies.